Radio Site Allocation Design

This module is performed to identify the detailed radio equipment and indoor/outdoor installation material list required to perform CW and TI services, and to provide RBS/BTS room plan and tower/mast/antenna locations.

At the end of this module, Radio Site Allocation Design part of Radio Site Engineering report is filled. All necessary equipment/material lists and drawings are included in the mentioned report.

Radio Site Cabling Design

This module is performed to identify the used feeder types and cabling routes/inlets details according to the Radio Network Design requirements.

At the end of this module, Radio Site Cabling Design part of Radio Site Engineering report is filled. All necessary feeder types and cabling route drawings are included in the mentioned report.

Civil Works Survey

Civil Work Survey is performed in order to identify details of the construction works to be realized in order to prepare radio site for telecom implementation. Static calculations and geotechnical investigation for rooftop sites, towers and masts are the main subjects to be clarified within this module. With general outline design input and the technical details, the constructions works can start.

At the end of this module, Civil Work Detailed Design report is prepared including all technical details and drawings mentioned above.

Warehouse & Logistics

Warehouse & Logistic is the key module within the whole CWTI services. As per the time is very important for the operators to launch the network, it is very crucial to have and to deliver necessary equipments and materials on time. This module is the one supports whole process where equipment and material storage and delivery is held in.

A very well defined and functioning process with experienced resources is essential in order to let this module working properly.

Construction Works

Construction works is the module where Civil Works service is realized. All construction related works and supportive systems such as battery backup, A/C are done according to the details given in the Civil Work Detailed Design report and the radio site made ready for Telecom Implementation.

At the end of this module, Civil Work Detailed Design report is updated with the changes from design details if there is any.

RBS/BTS Installation

RBS/BTS installation starts after the radio site construction works are completed. Antenna installation, feeder cables, cabinets and BTS equipments are installed and related cable/feeder connections are done in this module according to the Radio Site Engineering report.

At the end of this module, radio site becomes ready to be integrated to the network after installing the transmission equipments.

Transmission (TRM) Installation

Installation of transmission equipments starts after completing the RBS/BTS installation. Selected transmission media is installed and related connections are done according to Transmission Network Design Details.

At the end of this module, radio site becomes ready for test and commissioning.

Final Check

After all above modules are completed, final check of the installed site is performed in order to examine the work quality and to avoid any problem before test and commissioning. All works done during the radio site installation such as warning and naming labels, feeder installations, cable connections are checked for the convenience according to the defined standards and fixing. Any problem noticed at final check is corrected and the radio site is become ready to be integrated to the network.

Site installation binder containing all details about the installation of the radio site is prepared by combining all the documentation prepared at the end of each module. Updates are done according to the changes/corrections at final check.

Test & Commissioning

If all above modules are completed without any problem, radio site is ready to be integrated to the network. It is tested and integrated to the network within this module with the help of operator where necessary definitions in the network elements are done by the operator.

Acceptance Tests

Once the radio site is integrated to the network, Acceptance Tests are performed in order to examine whether the RF performance targets are achieved or not? These tests are basically realized in the field by drive testing and supported by statistical data if available. Measured values by drive test are compared with Acceptance Criteria defined by the customer. The acceptance criteria mainly covers the following tests; coverage, quality measurements, handover performance and congestion evaluation.

At the end of this module, pre-defined and agreed radio site acceptance report is filled with the measured values for the defined tests and the acceptance is done if all the results are fulfilling the requirements.

Reporting / Documentation Update

Reporting and Documentation after completion of each module is the base of all studies and works. Full details regarding to the whole provided service is provided within the reports and documentations. Drawings, pictures, user manuals and all other necessary papers are included in the documentation in order to be handed over to the customer at the end of the work.

In case of any change in the deigned or realized work, relevant document is immediately updated according to the real situation.

At the end of the whole service, Radio Site Details binder is prepared including CW, TI and Acceptance details and delivered to the customer.


 
RECENT NEWS

2008

-IRIS will attend to Mobile Communications Conference and Exhibition in Barcelona-SPAIN. You can come and visit our stand between 11-14 February 2008

-IRIS is doing Turnkey-Rollout for ZTE Uzbekistan Coscom Project

-IRIS is doing Radio&Transmission Network Planning and Transmission Optimization for NSN Uzbekistan Coscom Project

-IRIS performs 3G IP Testing for operators…

-IRIS is doing Radio&Transmission Network Planning and Transmission Optimization for Motorola,Vodafone Turkey

-IRIS completed 3G Model Tuning for Nokia Turkey

-Research & Development Department developing a new drive test and performance measurement tool

-Radio Network Optimisation and Benchmarking project for Turkcell continues…(8th Year)

-IRIS recently extended its services to Turkcell by providing resources to Regional Optimisation Departments

-IRIS is performing Radio Network Measurements and Analysis Project for Motorola in Turkey

-Performance Measurements and Analysis in a major Swap Project in East of Turkey for Siemens completed…

-Short and long term projects for Siemens in Syria and Turkey in progress…

-IRIS operations for Nokia and Ericsson in Saudi Arabia continue since last 7 years…

-Qualcomm University and Wiley Interactive Training Programs are now a part of our internal trainings

-IRIS Optimiser UMTS version is in internal usage…